Understanding Tenant Improvement Allowances

How TI allowances work, how they're structured, and what both landlords and tenants should consider during negotiations.

A tenant improvement allowance—often called TI or TIA—is a landlord contribution toward customizing a commercial space. TI allowances are a standard component of commercial lease negotiations, and understanding how they work helps both parties structure deals that meet their objectives.

What Is a Tenant Improvement Allowance?

A tenant improvement allowance is a sum provided by the landlord to fund buildout or renovation of the leased space. It's typically expressed as a dollar amount per square foot.

Example Calculation

Space size 2,500 SF
TI allowance $45 per SF
Total TI allowance $112,500

Allowance amounts vary based on market conditions, property type, lease term, tenant creditworthiness, and the condition of the space being leased. In competitive markets, landlords may offer larger allowances to attract desirable tenants. In tighter markets, tenants may accept lower allowances to secure preferred locations.

Key concept: TI allowances are not separate from the lease economics—they're part of the overall deal structure. Landlords typically recover allowance costs through the rent over the lease term. Both parties should evaluate TI allowances in context of the full financial picture, not in isolation.

How TI Allowances Are Structured

TI allowances can be delivered in several ways, each with different implications for cash flow and risk allocation.

Lump Sum at Signing or Commencement

The landlord provides the full allowance upfront. This shifts more risk to the landlord (funds disbursed before improvements are verified) but provides the tenant capital when it's needed most. More common with creditworthy tenants and established landlord-tenant relationships.

Reimbursement

The tenant funds construction and submits invoices or payment applications for reimbursement up to the allowance amount. This structure protects the landlord by ensuring funds are tied to actual completed work, while requiring the tenant to have working capital available during construction.

Direct Payment to Contractors

The landlord pays approved contractors directly. This gives landlords more oversight of the construction process while reducing the tenant's upfront capital requirements.

Amortized into Rent

The landlord funds improvements but adds the cost to rent over the lease term, typically with interest. This functions as a loan built into the lease. The tenant avoids upfront costs but pays more over time; the landlord earns a return on the capital provided.

Landlord Considerations

Reimbursement and amortization structures reduce risk by tying disbursement to completed work or recovering costs with interest. Lump sum payments may be appropriate for credit tenants or when competing for desirable lessees.

Tenant Considerations

Lump sum or direct payment structures reduce the need for construction capital. Amortized allowances preserve cash but increase total occupancy cost. Reimbursement structures require available working capital.

What TI Allowances Typically Cover

TI allowances generally apply to permanent improvements that become part of the building. The specific scope should be clearly defined in the lease.

Typically Included

Walls and partitions, flooring, ceilings, lighting, electrical and data infrastructure, HVAC modifications, plumbing for restrooms or break areas, built-in millwork, doors, and painting. Architectural and engineering fees may also be included.

Often Negotiable

Security systems, signage, window treatments, cabling, specialized equipment installation, and permit fees. Coverage varies by landlord and market practice.

Typically Excluded

Furniture, equipment, computers, phone systems, inventory, trade fixtures, and moving costs. These are generally tenant capital expenses outside the TI allowance scope.

For both parties: Clearly defining "Allowance Work" or "Tenant Improvements" in the lease prevents disputes later. Ambiguity about what qualifies for reimbursement creates friction during construction.

Turn-Key Buildout vs. TI Allowance

As an alternative to providing a TI allowance, landlords sometimes offer to deliver a finished, "turn-key" space built to the tenant's specifications. Each approach has tradeoffs.

TI Allowance

Tenant controls the buildout—selecting contractors, managing the project, and making design decisions. More flexibility but also more responsibility. Cost overruns beyond the allowance are the tenant's obligation.

Turn-Key

Landlord manages construction and delivers a finished space. Tenant has less control over timing, contractor selection, and details. The landlord bears construction risk but typically builds in contingency.

For landlords, turn-key arrangements provide control over building quality and contractor relationships. For tenants with specific operational requirements or design preferences, TI allowances typically offer more flexibility. The right approach depends on the parties' priorities and capabilities.

Key Negotiation Points

Beyond the dollar amount, several aspects of TI allowances are commonly negotiated.

Allowance Amount

Influenced by market conditions, lease term, tenant credit, and the space's existing condition. Both parties should understand local market norms and how the allowance fits into the overall deal economics.

Payment Structure and Timing

When and how funds are disbursed affects both parties' cash flow and risk. The structure should align with each party's financial position and risk tolerance.

Scope of Covered Improvements

A clear definition of what qualifies as "Tenant Improvements" prevents disputes. Broader definitions benefit tenants; narrower definitions give landlords more control over how funds are used.

Unused Allowance

Some leases allow unused TI funds to be applied as rent credit; others treat unused amounts as forfeited. This affects how both parties value the allowance.

Completion Deadlines

Landlords often require improvements to be completed within a specified period to receive the allowance. Tenants should ensure timelines account for permitting and construction realities.

Cost Overruns

Costs exceeding the allowance are typically the tenant's responsibility. Both parties should have realistic expectations about likely buildout costs before finalizing terms.

Approval Requirements

Landlords generally require approval of plans and sometimes contractors. The lease should specify approval processes and timelines to avoid delays.

Common Issues to Address

Realistic Cost Estimates

Both parties benefit when the allowance bears a reasonable relationship to actual buildout costs. Tenants should obtain contractor estimates before finalizing lease terms. Landlords should understand typical improvement costs for the intended use.

Construction Oversight

Landlords have a legitimate interest in ensuring improvements meet building standards and code requirements. Tenants need enough flexibility to build a functional space. The lease should balance these interests.

Restoration Requirements

Some leases require tenants to remove improvements at lease end; others allow or require improvements to remain. This affects both the tenant's end-of-lease costs and the landlord's flexibility with future tenants.

Delays and Disputes

Construction rarely goes exactly as planned. The lease should address how delays affect rent commencement, what happens if the landlord withholds approval, and how disputes about allowance disbursement are resolved.

Getting TI Terms Right

Tenant improvement allowances are a significant component of most commercial leases. For landlords, they're a tool for attracting tenants and an investment recovered through rent. For tenants, they're a source of capital for creating functional space and a factor in total occupancy cost.

Well-structured TI provisions align the parties' interests, set clear expectations, and reduce the potential for disputes during construction. Poorly drafted provisions create ambiguity that can strain the landlord-tenant relationship before it even begins.

This resource is provided for general informational purposes only and does not constitute legal advice. TI allowance terms vary significantly by market, property type, and transaction. If you have questions about a specific lease negotiation, please consult a qualified attorney.